An update issued by Mayo County Council set out the following works:

• Cloonmoore/Cloonlavish GWS: Civil contractor appointed, Winters Plant Hire, for network replacement (22km of pipeline) and connection to public mains and taking in charge by Irish Water. Civil works are 60% complete.

Additional funding of €1,295,000 has been approved by the Department of Housing, Local Government and Heritage (DHLGH), bringing the total funding allocation to €1,545,000.

• Downpatrick Head CWC: Civil contractor appointed, Winters Plant Hire, for construction of a new community water connection to serve 29 houses. Civil works commenced mid-September and are ongoing.

Additional funding of €109,558 was approved by the department, bringing the total funding allocation to €353,202. The total cost of the project is €430,147.

• Drimbane GWS: Civil contractor appointed, Joe Reilly Plant Hire, for network upgrade and amalgamation of the scheme with Abbeyquater GWS.

• DB 1 Bundle (Tooreen/ Aghamoore GWS, Midfield GWS, Killaturley GWS: Contractor Hydro International in the process of being appointed for upgrade works to the three schemes' water treatment plants. Funding of €850,000 has been approved for the upgrade works.

• Ballycroy GWS: Contractor Joe Reilly Plant Hire in the process of being appointed for upgrade works to the scheme's raw water pipeline. Civil works to commence later this month. Additional funding of €183,066 approved, bringing total funding to €383,066.

• Murrisk CWC: Funding of €5,068,670 was approved for a new community water connection. The detailed design phase of this project has commenced and is progressing. SDS Consulting Engineers are the council's appointed employers representative for this project.

• A civil contract for upgrade to the Midfield GWS network (€161,756 allocated funding) has been advertised on E-tender.

• The following projects are currently in the detailed design phase: Killasser network upgrade (€680,000), Irishtown GWS network upgrade, connection to public mains and taking in charge by Irish Water (€512,670), Johnstown Lavellyroe GWS network upgrade, connection to public mains and taking in charge by Irish Water (€600,000), and Tooreen/Aghamoore GWS upgrade (€200,000).