Frustration over continued delays in opening east Mayo primary healthcare centre

CONSIDERABLE disappointment and frustration at the continued delays in opening the Ballyhaunis Primary Healthcare Centre has been expressed by Councillor Alma Gallagher, following a further update received at Tuesday’s meeting of the HSE Regional Health Forum West.

Councillor Gallagher, who has consistently raised the issue since her election to Mayo County Council and appointment to the health forum in June 2024, once again tabled a question seeking confirmation of the official opening date.

In its response, the HSE confirmed that construction works have been completed and that the procurement and delivery of furniture and equipment are ongoing. However, the building has yet to be formally handed over by the developer to the HSE, as final building control certification and regulatory sign-offs remain outstanding.

While the HSE continues to anticipate that the centre will open before the end of 2026, Councillor Gallagher questioned the reliability of yet another anticipated opening date, given the history of the development.

“The lights are on, but no one is home,” she commented.

“Anyone driving past Ballyhaunis Primary Healthcare Centre can see what appears to be a completed building. The lights are on, furniture and equipment are being delivered, yet the doors remain firmly closed to the public.

“For over two years, I have been coming to the Regional Health Forum asking essentially the same question. The people of Ballyhaunis and the wider east Mayo community can be forgiven for being sceptical about yet another anticipated opening date.”

HISTORY OF MISSED DEADLINES

Councillor Gallagher set out a history of missed deadlines.

The original Agreement for Lease was signed in January 2018, with construction commencing in November 2019 before works stalled in May 2021.

Since then, a succession of assurances and revised timelines have been provided, she said.

September 2024: Anticipated occupation by the HSE before the end of 2025.

May 2025: Anticipated practical completion date missed.

December 2025: Electrical connections cited as delaying progress, with an anticipated opening in the first quarter of 2026.

February 2026: Handover anticipated in April, with services operational in July.

June 2026: Revised handover date of the end of July, with an anticipated opening date of October 1.

September 2026: Further assurances that the centre would be operational before the end of 2026.

She commented: “Here we are, approaching the end of November, with less than five weeks remaining in the year, and I am still asking when the people of Ballyhaunis will be able to walk through the doors of their new healthcare facility.

“We are approaching eight years since the original lease agreement was signed. That is an extraordinary length of time for a community to be waiting for essential healthcare infrastructure.”

Councillor Gallagher also raised concerns regarding the contractual arrangements underpinning the development, which was procured under the HSE’s Primary Care Operational Lease Model.

Under this model, a private developer finances and constructs the facility for subsequent occupation by the HSE under a lease arrangement, rather than the HSE directly commissioning and managing the construction of the building.

“I fully acknowledge the efforts of the HSE Primary Care Team and appreciate that building control regulations must be complied with. The safety of patients and staff cannot be compromised.

“However, what I find particularly concerning is that, seven years after construction commenced, we are now being told that the final hurdle rests with the private developer and is outside the direct control of the HSE.

“This raises legitimate questions about the effectiveness of the contractual arrangements, the level of oversight afforded to the HSE and the mechanisms available to enforce timely delivery,” she said.

“What specific certification remains outstanding? What deadline has the developer been given to address these issues? What contractual mechanisms are available to the HSE to expedite the formal handover?

“While the operational lease model may have financial advantages for the State, we must also examine whether sufficient contractual safeguards are in place to protect communities from prolonged delays in the delivery of essential public healthcare infrastructure.”

Councillor Gallagher called on the HSE to provide a definitive timeline for both the formal handover of the building and the commencement of healthcare services, together with clarity on the services that will be available from the outset and whether these will be introduced on a phased basis.

“I do not want to find ourselves returning to the Regional Health Forum in January or February, asking the same question and receiving yet another revised timeline,” she added.

“The people of Ballyhaunis have been exceptionally patient, but that patience is wearing very thin.”

“We have had enough anticipated dates. What we need now is an opening date and an open door.”